Buyer guides

Set a line output target and test it

Count saleable packs at the end of the line. Use the same package format, counting point and elapsed-time definition in the quotation and the factory acceptance test.

Work back from the shift target

A target of 12,000 saleable bottles in 360 available production minutes requires about 33.4 good bottles per minute. Write down how much shift time is reserved for cleaning and format changes. Allow additional capacity if short stops or rejects will reduce the good-pack count.

Agree the test before the run

Choose the bottle, closure, label, formula and fill quantity for each format to be tested. Set the run duration, sample count and tolerances for dose, closure and label position. Specify where rejects are counted and who records each stop.

Keep one record per format

Record elapsed time, acceptable packs and rejected packs at the agreed outfeed point. Check a stop and restart, then time a planned changeover if it is part of the purchase. Assign each open issue an owner and a retest condition.

How do I calculate sustained good-pack output?

Divide acceptable finished packs by the agreed elapsed minutes. If 960 packs reach the counting point in 30 minutes and 30 fail inspection, the sustained rate for that run is 31 good packs per minute.